Hub Redevelopment

​The Hub redevelopment is moving along well and we will be back in the building well before the end of the term. We have been given a rough date but I am not going to advertise it as the timeline for completion is proving to be a movable feast! Works currently being completed include:

  • All asbestos removed
  • External panelling and windows replaced
  • New internal facilities include: 2 meeting rooms and toilet facilities
  • Roof replaced
  • New flooring and cabinetry
  • Upgrade of electrical systems
  • Repainted to match the other school buildings.

We are incredibly fortunate to have the support of BCE for the redevelopment of our St Paul’s School Community Hub. We will be officially opening and blessing the new building at our Family Fun Day on Sunday 23rd of June.

Regular programming has been affected but we have been able to secure the use of the Parish Meeting Room (Under Year 3A) in E Block for many of these programs.